BLOG

ENGINEERING KEY TO R & R PROJECT SUCCESS

A pulp and paper mill in Alabama needed to replace a 28’ long X 8’ diameter, 34,000 lb. deaerator. The unit was located just below the roofline of a 100’ tall building.

The traditional method of lifting the piece through an opening in the roof could not be done due to overhead piping that would not only be costly to remove, but would completely shut down production at the mill.  The deaerator would have to be accessed through a hole the customer cut in the side of the building.

It was a job for Barnhart’s movable counterweight system, but the reach of the beam in its normal configuration wasn’t long enough. Barnhart’s engineering team got involved to modify the system and add extensions to give it its necessary length.

In addition to engineering challenges, there were tight clearances in the mill alleyway to set up a 600-ton hydraulic crane and assemble the system, plus just 7′ of overhead clearance above the unit. Still, the old unit was successfully removed and the new unit set to anchor bolts inside a building that was operational.  The job was completed a day ahead of schedule.

Posted in R & R | Tagged , , | Leave a comment

Bridge Project Utilizes Multiple Cranes and A Cool Tool

Barnhart’s Mount Vernon, Wash. branch recently completed a project that required tapping into their extensive equipment inventory.

Barnhart was hired to set a 220-foot-long pedestrian bridge over the Green River in  Kent, Wash. The lift of the Tukwila Pedestrian-Bicycle Bridge involved three cranes: the LS 348 300-ton crawler, AC1600 650-ton AT and the GMK 7550 550-ton AT.

The lift allowed Barnhart to use one of their cool tools, a passing triangle that allowed the team to pass and share the load between the 650 and the 550 while the crawler tracked the other end into the final position. Barnhart’s engineering team was involved in initially suggesting the methodology and ultimately reviewing and signing off on it.

Here is a short time-lapse video highlighting the lift.

.

Posted in Heavy Civil Construction, Heavy Lift | Tagged , , , , | Leave a comment

BARNHART HAULS “SHED ON STEROIDS”

Barnhart is no stranger to handling massive equipment and loads. We’ve erected the structure that held the world’s largest jumbotron and transported the components of the world’s largest tunnel boring machine.

Now you can add a couple of superloads, which Barnhart was hired to transport from Colorado to Wyoming, a trip of over 550 miles. Each load contained a compressor generator building with a pre-installed diesel engine and compressor inside. While it wasn’t the biggest cargo Barnhart has ever hauled, the loads were 20 feet wide, 22 feet high, 140 feet long and weighed around 400,000 lbs.

The trip started at the manufacturers in Colorado where two Barnhart teams from Los Angeles and Memphis converged and loaded the cargo onto two separate 8-line Eastrac trailers. For the first few days, the convoy maintained a speed ranging from 2 ½ to 25 miles per hour as it passed through small towns and along two-lane highways. Barnhart had to coordinate with utilities and municipalities along the route to raise traffic signals and power lines, plus they had to negotiate a roundabout, which took 45 minutes to complete.

The haul attracted attention and made the local news in Wyoming, where Gregory Cross, Barnhart’s heavy haul supervisor was quoted as describing the loads as “…a backyard shed on steroids.”In Wyoming, the load was too high to clear an Interstate 80 overpass, so both Eastrac trailers had to do a U-turn on the interstate. It was a maneuver that required assistance from the Wyoming Highway Patrol and highway traffic teams as motorists on both sides of the interstate had to stop while the load completed its turn.

Barnhart continued its circuitous route to the final destination, a natural gas pumping station. The project was completed a day ahead of schedule.

 

Posted in Heavy Haul | Tagged , , , | Leave a comment

PROUDLY AMERICAN

Next week, people across the United States will be celebrating July 4th with fireworks, festivities and backyard barbecues galore. For most people, it’s a day off from work to celebrate America’s 241st birthday.

It’s also a chance to reflect upon what’s great about America. Among the many gifts our country gives us, we are grateful for opportunity, freedom, and the ability to succeed through hard work.

our branches

Our branches (red dots) from sea to shining sea.

Barnhart is a proudly American company. We were founded in 1969 in Memphis with a single location – a kitchen table. In the beginning, our current president Alan Barnhart’s parents started and ran the family business from their home.

Today, Barnhart has 45 branches and 1300 employees. Our employees come from all regions of the country. They are engineers, project managers, salespeople, crane operators, mechanics, ironworkers, and truck drivers, just to name a few roles that are indispensible to the success of our company.

Our employees represent all political persuasions, cultures and ethnicities. It’s a melting pot that works together to get the job done for our customers. It’s a picture of America.

This 4th of July we salute our employees and the country that has given us so much.

Posted in Uncategorized | Tagged , | Leave a comment

Cool Tools and Planning Make Dryer Installation Successful

Barnhart specializes in remove and replace projects. We enjoy the challenge involved in safely extricating a component, which is often buried in a tight, congested space with limited access, and replacing it while causing minimal plant disruptions and downtime.

These kinds of projects get our engineering team’s creative juices flowing as they devise a plan of action using our cool tools and specialized rigging techniques to get the job done.

Sometimes we handle just the replacement portion of the project, which doesn’t necessarily require any less innovative engineering or tools. For a project at a wood and pulp mill in Maine, Barnhart’s job was to haul and set two Yankee dryers weighing 141 tons each. They started in onsite staging and were hauled a half mile utilizing six lines of PST to a raised building opening.

The dryers were then hoisted 20’ in the air to reach the building opening using 44A gantries with a rigging tray arrangement that incorporated a 16” slide track. Once at the elevation, Barnhart slid the dryers along the track and handed them off to a 450 J/R gantry.

Floor loading issues were a problem, and Barnhart had to use transverse beams to support our track system on load bearing points. In tight working conditions, Barnhart had to rig, lift and rotate the dryer using a spreader with a swivel hook in order to rough set the dryer on its support steel.

Despite these challenges, which also included tight tolerances, an accelerated schedule and logistical considerations, the dryer was installed safely and on schedule.

Posted in R & R | Tagged , , , , | Leave a comment

VETERANS HELP US FULFILL OUR MISSION

On Memorial Day, we will remember those in the armed forces who gave their lives for our country. We are grateful to them and to our military veterans for their service and sacrifice.

Veterans are part of the Barnhart team. They’ve found the culture and values of military life in many ways reflect what we’ve built within our company.

Take Sabrina who was a member of the U.S. Army. When she got out of the service she admits to being a little lost. Not content with flipping burgers, she was looking for a job with a purpose. At Barnhart she found her mission in logistics, a position she considers not your “typical 9 to 5 job.”

Barnhart’s approach to training and development was familiar. In the army, she had received extensive training, hands-on learning and developed leadership skills, all core components of the culture at Barnhart.

For Jim, a former Navy officer and current Barnhart engineer, the most important lesson he took away from the military service was how to be a servant leader, one who helps his troops do their jobs better. As a servant leader, he says, “We serve. We teach. We help our team be safe.”

Safety, service and continuous improvement are three of Barnhart’s company values. We are constantly training our teams, helping them develop new skills. Whether it’s an apprentice, a project manager or a crane operator, every member has an important role and is reliant on others to successfully complete the project.

“A military veteran is trained in the field to complete any tasks to the best of your ability,” Sabrina says. “…You’re trained to never give up and to give it your all.”

We admire that spirit and invite all veterans to consider Barnhart as your next post.

Posted in Human Resources | Tagged , , , | Leave a comment

PROJECTS RESULT IN TWO JOB OF THE YEAR AWARDS

Creative thinking and extensive planning resulted in two 2017 Job of the Year awards for Barnhart from the Specialized Crane and Rigging Association (SC&RA). Barnhart was recognized in the categories of “Rigging Job of the Year Under $150,000” and “Hauling Job of the Year 160,000-500,000 lbs.”

In the Rigging Job of the Year, Barnhart tackled an emergency project that involved the removal and replacement of a ground-level exchanger shell at a refinery. But due to restricted access to the shell, it wasn’t going to be easy.

Directly above the 17-foot-long shell was a tangle of live piping within two inches of the shell. It was also surrounded by instrumentation and structural steel. The alleyway to the exchanger was less than 30 feet wide and at 15 feet above grade elevation there was a 10-foot-wide overhang. The unit was also operational.

Barnhart determined that the solution for removing the shell would need to be “mobile, modular and maneuverable.” The team had five days to come up with an answer.


They devised a custom movable counterweight cantilever system called the M1A1, stacked components that resembled a tank. The M1A1 had 30 kips of counterweight secured to a 750-ton hydraulic turntable, which was attached to six lines of Goldhofer PSTe.

The M1A1 allowed Barnhart to maneuver and rotate 360 degrees in the 30 feet wide alleyway. The system was able to stab inside the exchanger, lift the shell in a very tight area, and rotate it 90 degrees for removal from the unit. The process was reversed for the replacement of the shell.

In the Hauling Job of the Year, Barnhart was hired to haul a new heat recovery system generator (HRSG) from Tulsa to Los Angeles, a 2,343-mile journey that crossed six states. The HRSG was roughly 43 feet long, 16 feet wide, 16 feet tall and it weighed 225,000 lbs. The center of gravity was not centered longitudinally, it was offset by 3.5’, so it would be a challenge getting the axle lines loaded evenly.

Barnhart designed a trailer configuration that utilized two Goldhofer six-line California style dual lane trailers with 7’ dollies, 9’1” axle spacings at 20’ wide.  The permitted dimensions of the trailer were 260’ long, 21’ wide, and 17’11” tall with axle loadings of 38,000 lbs. per line. Barnhart also used a gooseneck on the front trailer to maintain equal axle loadings on all axle lines.

The route required permitting in Oklahoma, Kansas, Texas, New Mexico, Arizona and California, 21 local and county permits and approval from 18 different local, county, and district Department of Transportation (DOT) supervisors. Barnhart enlisted and coordinated the help of bucket trucks and police escorts and obtained utility clearances from approximately a dozen different utility companies.

The haul route involved a variety of roadways: interstate, state highways, local, county, and farm roads. The route included dense city travel in LA, mountainous climbs in the desert, and tight gravel roads.

The project took approximately 11 weeks from start to finish, which included seven weeks for permitting, trailer mobilization and loading. The actual 2,343 haul took three weeks, a trek that was completed without a safety incident or any DOT citations.

Posted in Awards, Heavy Haul, Refinery | Tagged , , , , , | Leave a comment

VIDEO LIBRARY SHOWCASES SOME OF BARNHART’S BEST

While Barnhart performs and documents jobs of all sizes, the massive projects involving large equipment and oversize components are often hard to capture. Words and photos can’t always do a project justice.

An example was a lift of a towering column at a refinery in Illinois, which involved a bit of ingenuity. Instead of using a second crane to tail up the column we used the Goldhofer tailing device. Luckily, Barnhart captured it on video, so you can truly appreciate the scale of the project.

That’s just one of the many videos from our library where you can see our work and equipment in all their glory: videos on the GS800 girder transport system, modular lift towers, or the lift of a colossal jumbotron. While they may not be Hollywood blockbuster material, we think they’re pretty compelling. Check them out.

Posted in Heavy Lift | Tagged , , , , | Leave a comment

MIDWEST BRANCHES ONE-STOP SHOPS

Barnhart’s 32 branches are located all across the country. They include a string of Midwest locations stretching from Chicago to Lincoln, Nebraska and north into South Dakota.

This Midwest presence was established in 2014, when Barnhart acquired Crane Rental and Rigging. They inherited a fleet of more than 40 cranes and eight branches located in Omaha, Lincoln and South Sioux City, Neb.; Des Moines, Cedar Rapids, Davenport and Ames, Iowa; and Sioux Falls, S.D. Their service area also extends into southern Minnesota and northern Missouri.

The branches’ capabilities have grown far beyond the exceptional crane service – with up to a 500 ton crane – for which Crane Rental was known. Through Barnhart’s extensive nationwide network, they can tap into an arsenal of specialty equipment, innovative rigging systems, and the expertise of more than 40 engineers.

Services also include wind turbine up-tower services, project cargo logistics, customized industrial machinery moving and transportation solutions, including bridge crossing systems and dolly combinations.

Agriculture, ethanol, nuclear, chemical plants, petroleum refining, wind maintenance, and civil construction are just a few of the industries served by the Midwest branches.

According to Ted Hickson, regional director for Barnhart, “The advantage of being part of the Barnhart family for our customers is that we can meet their needs better with a much larger pool of equipment and manpower. We’re more of a one-stop shop for a variety of needs.”

Posted in Nuclear Power, Project Cargo Logistics, Refinery | Tagged , , , , | Leave a comment

SHORT NOTICE NO PROBLEM ON R & R JOB

R & R projects, the remove and replace variety, are often challenging, time-sensitive jobs performed during turnarounds and outages. These are the kinds of projects we relish.

During a turnaround at a refinery in California, Barnhart was given little notice on a complicated project to remove and replace four air grids. The grids, weighing 28,000 lbs. each, were located inside the regenerator of the fluid catalytic cracking (FCC) unit.

Barnhart was notified of the project on a Thursday. The team arrived on site on Friday and met with the customer. Then they got to work figuring out an efficient solution. Engineering was finalized and equipment and personnel were mobilized on Saturday. By Sunday, the team was ready to make the first pick.

The grids had to be navigated through some tight and congested spaces. Barnhart utilized their Moveable Counterweight Cantilever System due to its maneuverability on lifts needing lateral movement to avoid obstructions.

Some of the obstacles Barnhart encountered were platforms that interfered with the crane’s boom and additional structures that had to be avoided. The operation was also happening in a heavy traffic area, so safety was critical.

Despite these challenges, Barnhart removed the grids in one and a half shifts, a fraction of the estimated 14 shifts and seven days the customer had estimated the job would need. That quick turnaround during a turnaround, saved the customer considerable time and money.

Posted in R & R, Refinery | Tagged , , , , , | Leave a comment