Projects & Case Studies· Specialized Transport ·Pulp and Paper
0 Views
Barnhart was contracted to install multiple large components during a pulp and paper mill expansion in South Carolina. The original lift plan would have caused major disruption to ongoing work and slowed overall progress.
Instead, Barnhart engineered a custom solution that minimized interference with surrounding crews, reduced risk, and kept the project moving. Using a combination of specialized equipment and strategic planning, the team completed the job safely—several days ahead of schedule.
This project is a strong example of how Barnhart delivers smart solutions that save time and reduce impact, even on the most complex jobsites.
80,000 Pound Kiln Installation Project
View
Alternate Approach: One-Lift Vessel Removal
View
Cost Effective Approach to Up-Ending and Down-Ending a Power Plant Generator
View
Cutting Cost, Saving Time: Inside a Stabilizer Vessel Replacement Project
View
Lifting & Setting a 200 Ton Concrete Cap on a Historic Span Bridge
View
Non-Conventional Approach to Indiana Ball Mill Removal and Replacement Project
View
Problems Arise: Crafting Solutions During a Successful Steel Mill Installation Project
View
Safe and Efficient Rooftop Unit Installation
View
Smarter Dryer Replacement Inside a Tight Paper Mill Layout
View
Start to Finish: 200-Ton Caisson Transport
View
Successful Completion of Industrial Mining Project During Time Sensitive Outage
View
Using a Custom Lifting Beam to Replace Transformer Radiators
View
Barnhart’s Knoxville Team Delivers Big
View
135-Foot Ship Lift | Barnhart Heavy Lift Cranes Barge Loading & Marine Logistics
View
160-Foot Conveyor Lift and Set | Barnhart Project Spotlight
View
Custom Tools and Strand Jacks: Solving a Nuclear Outage Challenge
View
Barnhart’s Big Lift: Semiconductor Mega-Project
View
Barnhart’s 380K lbs Generator Transport Across 1,800 Miles
View
Inside the Move: 400,000 Pounds of Engineering Precision
View
Restacking a 430 Ton Generator On-Site: Tailling Beam & Telescoping Hydraulic Gantry
View
Taking Down Giants at a Pulp & Paper Mill
View
Barnhart's Temporary Overhead Crane System: Fast, Flexible, and Built for Safety
View
Heavyweight Champion: Barnhart’s 900-Ton Gantry Debut
View
Setting 20 Steel Bridge Girders Over I-55
View
The Barnhart Lift Table - Precise and Powerful Lifting
View
The Barnhart Push Up Unit System in Action
View
"So let's see what 36 axles and a million pounds looks like..."
View
Barnhart’s Goldhofer Platform Trailers: Modular Power for Heavy Transport
View
Completing Remove & Replace Days Ahead of Schedule with Custom Engineering
View
Going the Distance: Transporting International Cargo Over 1,100 Miles
View
Hauling a Huge Rotor Through Small Town Streets
View
Hauling and Setting Multi-Story Refinery Modules
View
Heaviest Cargo Ever Moved Across Mobile Bay
View
How We Simplify Super Heavy Transport - Project Cargo Logistics
View
If There's a Will, There's a Way: Transporting Oversized Loads at a Nuclear Power Station
View
Italy to Illinois: Transport and Installation of Four Texas Towers
View
Massive Coils Travel 49,000+ Accident-Free Miles
View
Moving 100+ Ton Components Two Stories High and Ahead of Schedule
View
Transport Over Rivers and Roads, Turbine Haul and Installation
View
Transporting a Massive Component Through a Snowy Minnesota Town
View
Turnkey Solutions for Project Cargo
View
Using Custom Solutions for Over the Road Transport | Barnhart Heavy Transport
View